You will need to notify us when you reach the following stages of work:

  • Commencement
  • Excavation of foundations (before concreting)
  • Preparation of the ground floor
  • Drains as laid (prior to covering)
  • Drains on test
  • Occupation
  • Completion

We may require further notification at the following stages:

  • Intermediate (first and second) floor constructions in place
  • Roof carcassing in place
  • Pre-plaster
  • Electrical wiring installed or being installed (where Part P Electrician is not used)
  • Structural beams and columns (prior to covering)

If you are in any doubt about when inspections will be required, please contact the Building Control team using the form at the bottom of the page for further guidance.